Action Date | Action Description |
---|---|
Apr 23, 2020 | Assent Application Received |
Apr 24, 2020 | Administrative Review for Completeness |
May 28, 2020 | Bio Team Review for Completeness |
May 29, 2020 | Deficient Application - Owner Notification Sent |
Jun 09, 2020 | Phone Call |
Jul 02, 2020 | Deficiency Response Received |
Jul 08, 2020 | Bio Team Review for Completeness |
Jul 08, 2020 | Application Accepted |
Jul 24, 2020 | HPHC Historical Preservation No Effect |
Jul 24, 2020 | HPHC Review Pending |
Jul 28, 2020 | Project Manager |
Aug 18, 2020 | Biologist Report |
Aug 19, 2020 | Typist for Processing |
Aug 19, 2020 | Executive Sign Off |
Aug 19, 2020 | Sent to Photo Copy |
Aug 19, 2020 | Permit Approved |
Aug 24, 2020 | Land Evidence Date |