Action Date | Action Description |
---|---|
May 06, 2020 | Assent Application Received |
May 13, 2020 | Administrative Review for Completeness |
May 13, 2020 | Bio Team Review for Completeness |
May 13, 2020 | Deficient Application - Owner Notification Sent |
Jun 23, 2020 | Deficiency Response Received |
Jul 01, 2020 | Bio Team Review for Completeness |
Jul 01, 2020 | Application Accepted |
Jul 08, 2020 | Project Manager |
Jul 10, 2020 | HPHC Review Pending |
Jul 10, 2020 | HPHC Historical Preservation No Effect |
Jul 30, 2020 | Typist for Processing |
Jul 30, 2020 | Executive Sign Off |
Jul 30, 2020 | Sent to Photo Copy |
Jul 30, 2020 | Permit Approved |
Jul 30, 2020 | Biologist Report |
Jan 13, 2021 | Land Evidence Date |
Jun 28, 2022 | Modification Request |
Jun 30, 2022 | Administrative Review for Completeness |
Jul 06, 2022 | Bio Team Review for Completeness |
Jul 07, 2022 | Project Manager |
Aug 02, 2022 | HPHC Historical Preservation No Effect |
Oct 06, 2022 | Biologist Report |
Oct 07, 2022 | Typist for Processing |
Oct 07, 2022 | Executive Sign Off |
Oct 07, 2022 | Sent to Photo Copy |
Oct 07, 2022 | Modification Approved |
Oct 13, 2022 | Permit Mailed |
Dec 13, 2022 | Land Evidence Date |