Action Date | Action Description |
---|---|
Apr 08, 2020 | Assent Application Received |
May 11, 2020 | Administrative Review for Completeness |
May 13, 2020 | Eng Team Review for Completeness |
May 13, 2020 | Application Accepted |
May 15, 2020 | Project Manager |
May 19, 2020 | HPHC Historical Preservation No Effect |
May 19, 2020 | HPHC Review Pending |
May 27, 2020 | Typist for Processing |
May 27, 2020 | Executive Sign Off |
May 27, 2020 | Permit Approved |
May 27, 2020 | Engineering Report |
May 11, 2021 | Maintenance/Repair/Location within the Marina Perimeter |
Jun 15, 2021 | Land Evidence Date |