Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
May 12, 2020 | Assent Application Received |
May 12, 2020 | Administrative Review for Completeness |
May 13, 2020 | Bio Team Review for Completeness |
May 13, 2020 | Application Accepted |
May 15, 2020 | Project Manager |
May 15, 2020 | Category A* (Docks) |
May 20, 2020 | HPHC Historical Preservation No Effect |
May 20, 2020 | HPHC Review Pending |
Jul 21, 2020 | Comments Received |
Jul 21, 2020 | Plans Received |
Jul 23, 2020 | 30 day Public Notice Issued |
Aug 23, 2020 | Public Notice End Date |
Sep 24, 2020 | Dock Meeting -- Approval |
Sep 24, 2020 | Biologist Report |
Sep 25, 2020 | Typist for Processing |
Oct 07, 2020 | Executive Sign Off |
Oct 07, 2020 | Permit Approved |
Oct 15, 2020 | Land Evidence Date |
Dec 07, 2020 | US Army Corps of Engineers Approval Received |