Application 2020-05-032 Details

Back to List


Actions:

Action Date Action Description
Dock Post-Construction Certification by Engineer received.
May 12, 2020 Assent Application Received
May 12, 2020 Administrative Review for Completeness
May 13, 2020 Bio Team Review for Completeness
May 13, 2020 Application Accepted
May 15, 2020 Project Manager
May 15, 2020 Category A* (Docks)
May 20, 2020 HPHC Historical Preservation No Effect
May 20, 2020 HPHC Review Pending
Jul 21, 2020 Comments Received
Jul 21, 2020 Plans Received
Jul 23, 2020 30 day Public Notice Issued
Aug 23, 2020 Public Notice End Date
Sep 24, 2020 Dock Meeting -- Approval
Sep 24, 2020 Biologist Report
Sep 25, 2020 Typist for Processing
Oct 07, 2020 Executive Sign Off
Oct 07, 2020 Permit Approved
Oct 15, 2020 Land Evidence Date
Dec 07, 2020 US Army Corps of Engineers Approval Received

Details:

File No
2020-05-032
Town
Narragansett
First Name
Dianne E Kwoka Rev. Trust
Last Name
Street
Penguin Drive
Location
9 Penguin Drive
Plat/Map
R-3
Lot/Block
19
Decision Date
Oct 07, 2020
Dock Reg.No
2403
Project
as-built residential boating facility
Description
Docks, Piers, Floats (Residential)
Water Area
Point Judith Pond (Great Island)
Easement
0
Acceptance Date
May 13, 2020

Back to List