Action Date | Action Description |
---|---|
May 26, 2020 | Assent Application Received |
Jun 05, 2020 | Administrative Review for Completeness |
Jun 09, 2020 | Bio Team Review for Completeness |
Jun 09, 2020 | Deficient Application - Owner Notification Sent |
Jun 19, 2020 | Deficiency Response Received |
Jul 01, 2020 | Bio Team Review for Completeness |
Jul 01, 2020 | Application Accepted |
Jul 08, 2020 | Project Manager |
Jul 10, 2020 | HPHC Review Pending |
Jul 10, 2020 | HPHC Historical Preservation No Effect |
Sep 14, 2020 | Additional Information Requested from Applicant |
Oct 08, 2020 | Additional Information Received |
Oct 14, 2020 | Additional Information Received |
Oct 14, 2020 | Typist for Processing |
Oct 14, 2020 | Executive Sign Off |
Oct 14, 2020 | Sent to Photo Copy |
Oct 14, 2020 | Permit Approved |
Oct 14, 2020 | Biologist Report |
Nov 04, 2020 | Land Evidence Date |
Jan 26, 2021 | Modification Request |
Jan 28, 2021 | Administrative Review for Completeness |
Feb 01, 2021 | Bio Team Review for Completeness |
Feb 01, 2021 | Project Manager |
Feb 16, 2021 | Additional Information Requested from Applicant |
Feb 17, 2021 | HPHC Historical Preservation No Effect |
Feb 17, 2021 | HPHC Review Pending |
Mar 02, 2021 | Plans Received |
Mar 02, 2021 | Plans Received |
Mar 04, 2021 | Stipulation Package from Biologist |
Mar 04, 2021 | Biologist Report |
Mar 09, 2021 | Typist for Processing |
Mar 09, 2021 | Executive Sign Off |
Mar 09, 2021 | Sent to Photo Copy |
Mar 09, 2021 | Plans Received |
Mar 09, 2021 | Modification Approved |