Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jun 15, 2020 | Assent Application Received |
Jun 16, 2020 | Administrative Review for Completeness |
Jun 17, 2020 | Category A* (Docks) |
Jun 17, 2020 | Eng Team Review for Completeness |
Jun 17, 2020 | Bio Team Review for Completeness |
Jun 17, 2020 | Application Accepted |
Jun 17, 2020 | Project Manager |
Jun 23, 2020 | 30 day Public Notice Issued |
Jun 29, 2020 | HPHC Review Pending |
Jun 29, 2020 | HPHC Historical Preservation No Effect |
Jul 23, 2020 | Public Notice End Date |
Sep 05, 2020 | Plans Received |
Sep 22, 2020 | Typist for Processing |
Sep 22, 2020 | Executive Sign Off |
Sep 22, 2020 | Sent to Photo Copy |
Sep 22, 2020 | Permit Approved |
Sep 22, 2020 | Biologist Report |
Sep 22, 2020 | Engineering Report |
Sep 24, 2020 | Land Evidence Date |