Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jun 26, 2020 | Assent Application Received |
Jun 26, 2020 | Administrative Review for Completeness |
Jul 21, 2020 | Project Manager |
Jul 21, 2020 | Eng Team Review for Completeness |
Jul 21, 2020 | Application Accepted |
Jul 21, 2020 | Category A* (Docks) |
Aug 05, 2020 | 30 day Public Notice Issued |
Aug 11, 2020 | Additional Information Received |
Sep 05, 2020 | Public Notice End Date |
Nov 09, 2020 | Executive Sign Off |
Nov 09, 2020 | Sent to Photo Copy |
Nov 09, 2020 | Stipulation Package by Engineer |
Nov 09, 2020 | Typist for Processing |
Nov 09, 2020 | Permit Approved |
Nov 09, 2020 | Engineering Report |
Dec 29, 2020 | Land Evidence Date |