Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jul 01, 2020 | Assent Application Received |
Jul 01, 2020 | Administrative Review for Completeness |
Jul 02, 2020 | Eng Team Review for Completeness |
Jul 02, 2020 | Application Accepted |
Jul 02, 2020 | Category A* (Docks) |
Jul 08, 2020 | HPHC Review Pending |
Jul 08, 2020 | HPHC Historical Preservation No Effect |
Jul 17, 2020 | 30 day Public Notice Issued |
Aug 17, 2020 | Public Notice End Date |
Sep 29, 2020 | Correspondence Received |
Oct 14, 2020 | Dock Meeting Scheduled (Admin) |
Dec 03, 2020 | Stipulation Package by Engineer |
Dec 03, 2020 | Typist for Processing |
Dec 03, 2020 | Executive Sign Off |
Dec 03, 2020 | Sent to Photo Copy |
Dec 03, 2020 | Permit Approved |
Dec 03, 2020 | Project Manager |
Dec 03, 2020 | Engineering Report |
Dec 13, 2020 | Land Evidence Date |
Aug 28, 2023 | Additional Information Requested from Applicant |