Action Date | Action Description |
---|---|
Jul 07, 2020 | Assent Application Received |
Jul 07, 2020 | Administrative Review for Completeness |
Jul 14, 2020 | Bio Team Review for Completeness |
Jul 14, 2020 | Additional Information Received |
Jul 16, 2020 | Deficient Application - Owner Notification Sent |
Sep 17, 2020 | Deficiency Response Received |
Sep 24, 2020 | Bio Team Review for Completeness |
Sep 24, 2020 | Application Accepted |
Oct 01, 2020 | Project Manager |
Oct 13, 2020 | Additional Information Requested from Applicant |
Oct 13, 2020 | Plans Received |
Oct 14, 2020 | Plans Received |
Oct 20, 2020 | Typist for Processing |
Oct 20, 2020 | Executive Sign Off |
Oct 20, 2020 | Permit Approved |
Oct 20, 2020 | Biologist Report |
Oct 20, 2020 | HPHC Review Pending |
Oct 26, 2020 | HPHC Historical Preservation No Effect |
Oct 30, 2020 | Land Evidence Date |