Action Date | Action Description |
---|---|
Jul 20, 2020 | Dredge Application |
Jul 20, 2020 | Administrative Review for Completeness |
Jul 21, 2020 | Application Accepted |
Jul 21, 2020 | Project Manager |
Jul 21, 2020 | Eng Team Review for Completeness |
Jul 24, 2020 | HPHC Historical Preservation No Effect |
Feb 04, 2021 | Stipulation Package by Engineer |
Feb 04, 2021 | CHA -- application modified due to CHA info |
Feb 04, 2021 | Engineering Report |
Feb 05, 2021 | Typist for Processing |
Feb 05, 2021 | Executive Sign Off |
Feb 05, 2021 | Sent to Photo Copy |
Feb 05, 2021 | Permit Approved |
Jun 15, 2021 | Land Evidence Date |
Mar 17, 2022 | CAD Cell Fee Due - initial (letter) |
Mar 17, 2022 | CAD Cell Fee (initial) received |
Mar 17, 2022 | CAD Cell Fee Due-Final |