Action Date | Action Description |
---|---|
Jul 29, 2020 | Assent Application Received |
Jul 29, 2020 | Administrative Review for Completeness |
Aug 11, 2020 | Bio Team Review for Completeness |
Aug 11, 2020 | Deficient Application - Owner Notification Sent |
Aug 26, 2020 | Deficiency Response Received |
Sep 11, 2020 | Administrative Review for Completeness |
Sep 14, 2020 | Bio Team Review for Completeness |
Sep 14, 2020 | Application Accepted |
Sep 14, 2020 | Project Manager |
Sep 30, 2020 | Additional Information Requested from Applicant |
Oct 02, 2020 | Additional Information Received |
Oct 02, 2020 | Typist for Processing |
Oct 02, 2020 | Biologist Report |
Oct 06, 2020 | HPHC Review Pending |
Oct 06, 2020 | HPHC Historical Preservation No Effect |
Oct 07, 2020 | Executive Sign Off |
Oct 07, 2020 | Sent to Photo Copy |
Oct 07, 2020 | Permit Approved |
Oct 15, 2020 | Land Evidence Date |
Aug 25, 2021 | Assent Correction Request Received |
Aug 26, 2021 | Assent Correction Mailed |