Action Date | Action Description |
---|---|
Aug 05, 2020 | Assent Application Received |
Aug 05, 2020 | Administrative Review for Completeness |
Sep 08, 2020 | Additional Information Received |
Sep 22, 2020 | Application Accepted |
Sep 22, 2020 | Biologist Report |
Sep 22, 2020 | Bio Team Review for Completeness |
Oct 06, 2020 | HPHC Review Pending |
Oct 06, 2020 | HPHC Historical Preservation No Effect |
Oct 07, 2020 | Executive Sign Off |
Oct 07, 2020 | Sent to Photo Copy |
Oct 07, 2020 | Permit Approved |
Oct 07, 2020 | Typist for Processing |
Oct 23, 2020 | Land Evidence Date |