Action Date | Action Description |
---|---|
Aug 14, 2020 | Assent Application Received |
Aug 14, 2020 | Administrative Review for Completeness |
Aug 17, 2020 | Additional Information Requested from Applicant |
Aug 20, 2020 | Additional Information Received |
Aug 31, 2020 | Project Manager |
Aug 31, 2020 | Application Accepted |
Aug 31, 2020 | Bio Team Review for Completeness |
Sep 22, 2020 | Biologist Report |
Sep 22, 2020 | Additional Information Requested from Applicant |
Sep 22, 2020 | Correspondence Received |
Sep 22, 2020 | Typist for Processing |
Sep 22, 2020 | Executive Sign Off |
Sep 22, 2020 | Sent to Photo Copy |
Sep 22, 2020 | Permit Approved |
Oct 06, 2020 | HPHC Review Pending |
Oct 06, 2020 | HPHC Historical Preservation No Effect |
Oct 26, 2020 | Duplicate Original Assent requested/mailed |
Nov 23, 2020 | Land Evidence Date |