Action Date | Action Description |
---|---|
Aug 18, 2020 | Assent Application Received |
Aug 18, 2020 | Administrative Review for Completeness |
Aug 25, 2020 | Eng Team Review for Completeness |
Aug 25, 2020 | Bio Team Review for Completeness |
Aug 31, 2020 | Project Manager |
Aug 31, 2020 | Application Accepted |
Sep 16, 2020 | Joint Public Notice |
Sep 22, 2020 | HPHC Review Pending |
Sep 22, 2020 | HPHC Historical Preservation No Effect |
Oct 17, 2020 | Public Notice End Date |
Oct 20, 2020 | Water Quality Certification |
Dec 04, 2020 | Additional Information Requested from Applicant |
Dec 18, 2020 | Additional Information Received |
Jan 15, 2021 | US Army Corps of Engineers Approval Received |
May 17, 2021 | Stipulation Package by Engineer |
May 17, 2021 | Stipulation Package from Biologist |
May 17, 2021 | Biologist Report |
May 17, 2021 | Engineering Report |
May 19, 2021 | Typist for Processing |
May 25, 2021 | Executive Sign Off |
May 25, 2021 | Sent to Photo Copy |
May 25, 2021 | Permit Approved |
Aug 19, 2021 | Land Evidence Date |