Application 2020-08-038 Details

Back to List


Actions:

Action Date Action Description
Aug 18, 2020 Assent Application Received
Aug 18, 2020 Administrative Review for Completeness
Aug 25, 2020 Eng Team Review for Completeness
Aug 25, 2020 Bio Team Review for Completeness
Aug 31, 2020 Project Manager
Aug 31, 2020 Application Accepted
Sep 16, 2020 Joint Public Notice
Sep 22, 2020 HPHC Review Pending
Sep 22, 2020 HPHC Historical Preservation No Effect
Oct 17, 2020 Public Notice End Date
Oct 20, 2020 Water Quality Certification
Dec 04, 2020 Additional Information Requested from Applicant
Dec 18, 2020 Additional Information Received
Jan 15, 2021 US Army Corps of Engineers Approval Received
May 17, 2021 Stipulation Package by Engineer
May 17, 2021 Stipulation Package from Biologist
May 17, 2021 Biologist Report
May 17, 2021 Engineering Report
May 19, 2021 Typist for Processing
May 25, 2021 Executive Sign Off
May 25, 2021 Sent to Photo Copy
May 25, 2021 Permit Approved
Aug 19, 2021 Land Evidence Date

Details:

File No
2020-08-038
Town
Portsmouth
First Name
Town of Portsmouth
Last Name
Street
Narragansett Avenue
Location
Narragansett Avenue
Plat/Map
Lot/Block
Decision Date
May 25, 2021
Dock Reg.No
Project
replace existing 6' wide x 3' high concrete arch culvert over Mill Creek
Description
Roadways, Bridges, Pk Lots, Rr Line (Pri
Water Area
Easement
0
Acceptance Date
Aug 31, 2020