Action Date | Action Description |
---|---|
Aug 21, 2020 | Assent Application Received |
Sep 11, 2020 | Administrative Review for Completeness |
Sep 14, 2020 | Bio Team Review for Completeness |
Sep 14, 2020 | Project Manager |
Sep 14, 2020 | Application Accepted |
Sep 30, 2020 | Phone Call |
Oct 06, 2020 | HPHC Review Pending |
Oct 06, 2020 | HPHC Historical Preservation No Effect |
Oct 13, 2020 | Biologist Report |
Oct 14, 2020 | Typist for Processing |
Oct 14, 2020 | Executive Sign Off |
Oct 14, 2020 | Sent to Photo Copy |
Oct 14, 2020 | Permit Approved |
Oct 30, 2020 | Land Evidence Date |
Oct 28, 2021 | Phone Call |
Nov 01, 2021 | Modification Request |
Nov 12, 2021 | Administrative Review for Completeness |
Nov 17, 2021 | Bio Team Review for Completeness |
Dec 09, 2021 | HPHC Review Pending |
Dec 09, 2021 | HPHC Historical Preservation No Effect |
Jan 05, 2022 | Biologist Report |
Jan 06, 2022 | Typist for Processing |
Jan 06, 2022 | Executive Sign Off |
Jan 06, 2022 | Sent to Photo Copy |
Jan 06, 2022 | Modification Approved |
Jan 10, 2022 | Permit Mailed |
Jan 24, 2022 | Land Evidence Date |