Action Date | Action Description |
---|---|
Aug 24, 2020 | Assent Application Received |
Sep 11, 2020 | Administrative Review for Completeness |
Sep 14, 2020 | Bio Team Review for Completeness |
Sep 14, 2020 | Application Accepted |
Sep 14, 2020 | Project Manager |
Sep 22, 2020 | HPHC Historical Preservation No Effect |
Sep 22, 2020 | HPHC Review Pending |
Nov 13, 2020 | Stipulation Package from Biologist |
Nov 13, 2020 | Typist for Processing |
Nov 13, 2020 | Executive Sign Off |
Nov 13, 2020 | Sent to Photo Copy |
Nov 13, 2020 | Permit Approved |
Nov 13, 2020 | Biologist Report |
Dec 01, 2020 | Assent Correction Request Received |
Dec 22, 2020 | Land Evidence Date |