Action Date | Action Description |
---|---|
Sep 01, 2020 | Dredge Application |
Sep 11, 2020 | Administrative Review for Completeness |
Sep 16, 2020 | Eng Team Review for Completeness |
Sep 16, 2020 | Project Manager |
Sep 16, 2020 | Application Accepted |
Sep 21, 2020 | 30 day Public Notice Issued |
Oct 21, 2020 | Public Notice End Date |
Oct 23, 2020 | Engineering Report |
Oct 27, 2020 | Stipulation Package by Engineer |
Oct 27, 2020 | Typist for Processing |
Oct 27, 2020 | Executive Sign Off |
Oct 27, 2020 | Permit Approved |
Oct 27, 2020 | HPHC Historical Preservation No Effect |
Oct 28, 2020 | Water Quality Certification |
Nov 06, 2020 | Land Evidence Date |
Feb 26, 2021 | CAD Cell Fee Due - initial (letter) |
Feb 26, 2021 | CAD Cell Fee (initial) received |
Mar 01, 2021 | Additional Information Received |
Apr 05, 2021 | CAD Cell Fee Due-Final |