Action Date | Action Description |
---|---|
Sep 15, 2020 | Dredge Application |
Sep 22, 2020 | Administrative Review for Completeness |
Sep 22, 2020 | Application Accepted |
Sep 22, 2020 | Eng Team Review for Completeness |
Sep 23, 2020 | 30 day Public Notice Issued |
Oct 23, 2020 | Public Notice End Date |
Nov 19, 2020 | Engineering Report |
Nov 20, 2020 | Typist for Processing |
Nov 20, 2020 | Executive Sign Off |
Nov 20, 2020 | Sent to Photo Copy |
Nov 20, 2020 | Permit Approved |
Nov 20, 2020 | Project Manager |
Nov 20, 2020 | Stipulation Package by Engineer |
Nov 20, 2020 | Water Quality Certification |
Dec 18, 2020 | CHA -- application modified due to CHA info |
Feb 26, 2021 | CAD Cell Fee Due - initial (letter) |
Feb 26, 2021 | CAD Cell Fee (initial) received |
Mar 01, 2021 | Additional Information Received |
Apr 05, 2021 | CAD Cell Fee Due-Final |
Aug 20, 2021 | Land Evidence Date |