Action Date | Action Description |
---|---|
Sep 15, 2020 | Assent Application Received |
Sep 22, 2020 | Administrative Review for Completeness |
Sep 30, 2020 | Additional Information Requested from Applicant |
Oct 02, 2020 | Additional Information Received |
Oct 07, 2020 | Application Accepted |
Oct 07, 2020 | Project Manager |
Oct 07, 2020 | Bio Team Review for Completeness |
Oct 26, 2020 | HPHC Review Pending |
Oct 26, 2020 | HPHC Historical Preservation No Effect |
Oct 27, 2020 | Additional Information Requested from Applicant |
Oct 28, 2020 | Correspondence Received |
Oct 28, 2020 | Correspondence Mailed/Faxed/E-mailed |
Nov 20, 2020 | Correspondence Mailed/Faxed/E-mailed |
Nov 20, 2020 | Additional Information Received |
Nov 30, 2020 | Stipulation Package from Biologist |
Nov 30, 2020 | Biologist Report |
Dec 01, 2020 | Typist for Processing |
Dec 01, 2020 | Executive Sign Off |
Dec 01, 2020 | Sent to Photo Copy |
Dec 01, 2020 | Permit Approved |
Jun 14, 2021 | Land Evidence Date |