Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Sep 21, 2020 | Assent Application Received |
Sep 23, 2020 | Administrative Review for Completeness |
Sep 28, 2020 | Bio Team Review for Completeness |
Sep 28, 2020 | Application Accepted |
Sep 29, 2020 | Project Manager |
Sep 29, 2020 | Category A* (Docks) |
Oct 06, 2020 | HPHC Review Pending |
Oct 06, 2020 | HPHC Historical Preservation No Effect |
Oct 15, 2020 | 30 day Public Notice Issued |
Oct 20, 2020 | Correspondence Received |
Nov 14, 2020 | Public Notice End Date |
Nov 18, 2020 | Dock Meeting -- Approval |
Nov 23, 2020 | Stipulation Package from Biologist |
Nov 23, 2020 | Typist for Processing |
Nov 23, 2020 | Executive Sign Off |
Nov 23, 2020 | Sent to Photo Copy |
Nov 23, 2020 | Permit Approved |
Nov 23, 2020 | Biologist Report |
Dec 11, 2020 | Land Evidence Date |