Action Date | Action Description |
---|---|
Sep 21, 2020 | Maintenance Certification Request |
Sep 23, 2020 | Administrative Review for Completeness |
Sep 24, 2020 | Bio Team Review for Completeness |
Sep 24, 2020 | Application Accepted |
Sep 24, 2020 | Project Manager |
Oct 01, 2020 | Correspondence Received |
Oct 06, 2020 | HPHC Historical Preservation No Effect |
Oct 06, 2020 | HPHC Review Pending |
Oct 29, 2020 | Correspondence Received |
Nov 19, 2020 | Correspondence Received |
Dec 10, 2020 | Additional Information Received |
Jan 12, 2021 | Additional Information Received |
Jan 25, 2021 | Additional Information Received |
Feb 12, 2021 | Stipulation Package from Biologist |
Feb 12, 2021 | Category A assigned |
Feb 12, 2021 | Typist for Processing |
Feb 12, 2021 | Permit Approved |
Feb 12, 2021 | Executive Sign Off |
Feb 12, 2021 | Sent to Photo Copy |
Feb 12, 2021 | Biologist Report |
Feb 18, 2021 | Land Evidence Date |
Feb 27, 2024 | Correspondence Received |