Action Date | Action Description |
---|---|
Sep 28, 2020 | Assent Application Received |
Sep 29, 2020 | Administrative Review for Completeness |
Sep 30, 2020 | Additional Information Requested from Applicant |
Sep 30, 2020 | Additional Information Requested from Applicant |
Oct 20, 2020 | Correspondence Mailed/Faxed/E-mailed |
Oct 29, 2020 | Additional Information Received |
Oct 29, 2020 | Application Accepted |
Oct 29, 2020 | Bio Team Review for Completeness |
Oct 30, 2020 | Project Manager |
Nov 25, 2020 | HPHC Historical Preservation No Effect |
Nov 25, 2020 | HPHC Review Pending |
Dec 01, 2020 | Stipulation Package from Biologist |
Dec 01, 2020 | Typist for Processing |
Dec 01, 2020 | Executive Sign Off |
Dec 01, 2020 | Sent to Photo Copy |
Dec 01, 2020 | Permit Approved |
Dec 01, 2020 | Biologist Report |
Dec 14, 2020 | Land Evidence Date |
Jun 09, 2022 | Modification Request |
Jun 14, 2022 | Administrative Review for Completeness |
Jun 24, 2022 | Bio Team Review for Completeness |
Jul 22, 2022 | HPHC Historical Preservation No Effect |
Aug 04, 2022 | Biologist Report |
Aug 05, 2022 | Typist for Processing |
Aug 05, 2022 | Executive Sign Off |
Aug 05, 2022 | Sent to Photo Copy |
Aug 05, 2022 | Modification Approved |
Aug 15, 2022 | Land Evidence Date |