Action Date | Action Description |
---|---|
Oct 05, 2020 | Assent Application Received |
Oct 05, 2020 | Administrative Review for Completeness |
Oct 13, 2020 | Bio Team Review for Completeness |
Oct 13, 2020 | Application Accepted |
Oct 13, 2020 | Project Manager |
Oct 26, 2020 | HPHC Historical Preservation No Effect |
Oct 27, 2020 | Additional Information Requested from Applicant |
Oct 30, 2020 | Phone Call |
Nov 04, 2020 | Additional Information Received |
Nov 06, 2020 | Stipulation Package from Biologist |
Nov 06, 2020 | Typist for Processing |
Nov 06, 2020 | Executive Sign Off |
Nov 06, 2020 | Sent to Photo Copy |
Nov 06, 2020 | Permit Approved |
Nov 06, 2020 | Biologist Report |
Nov 23, 2020 | Land Evidence Date |
Feb 24, 2023 | Modification Request |
Mar 01, 2023 | Administrative Review for Completeness |
Mar 29, 2023 | Bio Team Review for Completeness |
Mar 29, 2023 | Project Manager |
Apr 04, 2023 | Modification Approved |
Apr 04, 2023 | Biologist Report |
Apr 06, 2023 | Permit Mailed |
May 04, 2023 | HPHC Historical Preservation No Effect |
Oct 04, 2024 | Land Evidence Date |