Action Date | Action Description |
---|---|
Oct 14, 2020 | Freshwater Wetland - Preliminary Determination |
Oct 14, 2020 | Administrative Review for Completeness |
Oct 15, 2020 | Bio Team Review for Completeness |
Oct 15, 2020 | Application Accepted |
Oct 16, 2020 | Project Manager |
Oct 27, 2020 | HPHC Historical Preservation No Effect |
Oct 27, 2020 | HPHC Review Pending |
Nov 16, 2020 | Additional Information Requested from Applicant |
Nov 24, 2020 | Additional Information Received |
Nov 24, 2020 | Stipulation Package from Biologist |
Nov 24, 2020 | Typist for Processing |
Nov 24, 2020 | Executive Sign Off |
Nov 24, 2020 | Permit Approved |
Nov 24, 2020 | Biologist Report |
Dec 01, 2020 | Land Evidence Date |
Feb 10, 2023 | Modification Request |
Feb 20, 2023 | Administrative Review for Completeness |
Feb 24, 2023 | Additional Information Requested from Applicant |
Feb 28, 2023 | Correspondence Received |
Mar 02, 2023 | Plans Received |
Mar 16, 2023 | Application Accepted |
Mar 16, 2023 | Bio Team Review for Completeness |
Mar 16, 2023 | Project Manager |
Mar 22, 2023 | HPHC Historical Preservation No Effect |
Apr 13, 2023 | Biologist Report |
Apr 19, 2023 | Typist for Processing |
Apr 19, 2023 | Executive Sign Off |
Apr 19, 2023 | Sent to Photo Copy |
Apr 24, 2023 | Modification Approved |
Apr 25, 2023 | Permit Mailed |
May 01, 2023 | Land Evidence Date |