Action Date | Action Description |
---|---|
Oct 21, 2020 | Maintenance Certification Request |
Oct 22, 2020 | Administrative Review for Completeness |
Nov 04, 2020 | Eng Team Review for Completeness |
Nov 04, 2020 | Application Accepted |
Nov 04, 2020 | Project Manager |
Nov 25, 2020 | HPHC Historical Preservation No Effect |
Nov 25, 2020 | HPHC Review Pending |
Dec 07, 2020 | Plans Received |
Jan 11, 2021 | Stipulation Package by Engineer |
Jan 11, 2021 | Engineering Report |
Jan 12, 2021 | Typist for Processing |
Jan 12, 2021 | Executive Sign Off |
Jan 12, 2021 | Sent to Photo Copy |
Jan 12, 2021 | Permit Approved |