Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Oct 23, 2020 | Assent Application Received |
Oct 23, 2020 | Administrative Review for Completeness |
Nov 24, 2020 | Category A* (Docks) |
Nov 24, 2020 | Eng Team Review for Completeness |
Nov 24, 2020 | Application Accepted |
Nov 24, 2020 | Project Manager |
Dec 08, 2020 | 30 day Public Notice Issued |
Dec 23, 2020 | HPHC Review Pending |
Dec 23, 2020 | HPHC Historical Preservation No Effect |
Jan 08, 2021 | Public Notice End Date |
Jan 29, 2021 | Plans Received |
Mar 02, 2021 | Stipulation Package by Engineer |
Mar 02, 2021 | Permit Approved |
Mar 02, 2021 | Typist for Processing |
Mar 02, 2021 | Executive Sign Off |
Mar 02, 2021 | Sent to Photo Copy |
Mar 02, 2021 | Engineering Report |
Oct 13, 2021 | Land Evidence Date |