Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Nov 13, 2020 | Assent Application Received |
Nov 17, 2020 | Administrative Review for Completeness |
Nov 24, 2020 | Bio Team Review for Completeness |
Nov 24, 2020 | Application Accepted |
Nov 24, 2020 | Project Manager |
Nov 25, 2020 | Category A* (Docks) |
Dec 14, 2020 | 30 day Public Notice Issued |
Jan 12, 2021 | Objections/Comments Received |
Jan 13, 2021 | HPHC Historical Preservation No Effect |
Jan 13, 2021 | HPHC Review Pending |
Jan 14, 2021 | Public Notice End Date |
Apr 26, 2021 | Correspondence Received |
Jun 28, 2021 | Additional Information Received |
Oct 13, 2021 | Additional Information Received |
Nov 04, 2021 | Typist for Processing |
Nov 04, 2021 | Permit Approved |
Nov 04, 2021 | Engineering Report |
Nov 05, 2021 | Permit Mailed |
Nov 05, 2021 | Executive Sign Off |
Nov 15, 2021 | Land Evidence Date |