Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Nov 16, 2020 | Assent Application Received |
Nov 18, 2020 | Administrative Review for Completeness |
Nov 25, 2020 | Category A* (Docks) |
Dec 23, 2020 | Application Accepted |
Dec 23, 2020 | Project Manager |
Dec 23, 2020 | Bio Team Review for Completeness |
Dec 29, 2020 | Category A* (Docks) |
Feb 05, 2021 | HPHC Historical Preservation No Effect |
Feb 05, 2021 | HPHC Review Pending |
Sep 09, 2021 | 30 day Public Notice Issued |
Oct 09, 2021 | Public Notice End Date |
Oct 14, 2021 | Dock/1.1.6 Review approval |
Jan 20, 2022 | Biologist Report |
Jan 26, 2022 | Permit Approved |
Jan 26, 2022 | Typist for Processing |
Jan 26, 2022 | Executive Sign Off |
Jan 26, 2022 | Sent to Photo Copy |
Feb 01, 2022 | Permit Mailed |
Feb 18, 2022 | Land Evidence Date |