Action Date | Action Description |
---|---|
Nov 18, 2020 | Freshwater Wetland - Preliminary Determination |
Nov 20, 2020 | Administrative Review for Completeness |
Dec 08, 2020 | Bio Team Review for Completeness |
Dec 08, 2020 | Application Accepted |
Dec 08, 2020 | Project Manager |
Dec 15, 2020 | Additional Information Requested from Applicant |
Dec 23, 2020 | HPHC Historical Preservation No Effect |
Dec 23, 2020 | HPHC Review Pending |
Feb 02, 2021 | 30-Day Notification of Cancellation letter |
Feb 03, 2021 | Additional Information Received |
Mar 01, 2021 | Stipulation Package from Biologist |
Mar 01, 2021 | Permit Approved |
Mar 01, 2021 | Biologist Report |
Mar 01, 2021 | Typist for Processing |
Mar 01, 2021 | Executive Sign Off |
Mar 01, 2021 | Sent to Photo Copy |
Mar 12, 2021 | Land Evidence Date |
Jul 06, 2021 | Commencement of Work Notice received |
Jul 28, 2021 | Monitoring Report |
Dec 02, 2021 | Monitoring Report |
Jul 15, 2022 | Commencement of Work Notice received |
Nov 04, 2022 | Monitoring Report |
Jul 14, 2023 | Monitoring Report |
Oct 18, 2023 | Monitoring Report |
Nov 14, 2023 | Extension of Permit Request |
Nov 29, 2023 | Enforcement Compliance Inspection Required |
Nov 30, 2023 | Process Extension |
Nov 30, 2023 | Typist for Processing |
Nov 30, 2023 | Executive Sign Off |
Nov 30, 2023 | Sent to Photo Copy |
Nov 30, 2023 | Extension Approved |