Action Date | Action Description |
---|---|
Ready to Schedule Semi-Monthly Meeting | |
Dec 14, 2020 | Dredge Application |
Dec 15, 2020 | Administrative Review for Completeness |
Dec 15, 2020 | Eng Team Review for Completeness |
Dec 15, 2020 | Application Accepted |
Dec 15, 2020 | Project Manager |
Dec 21, 2020 | 15 day Public Notice Issued |
Dec 22, 2020 | Objections/Comments Received |
Jan 11, 2021 | Public Notice End Date |
Jan 14, 2021 | Entry of Appearance Received |
Jan 15, 2021 | Correspondence Received |
Jan 15, 2021 | HPHC Historical Preservation No Effect |
Feb 25, 2021 | Correspondence Received |
Oct 06, 2021 | Correspondence Received |
Dec 22, 2021 | Plans Received |
Apr 19, 2022 | Engineering Report |
May 10, 2022 | Mail Agenda Notice |
May 18, 2022 | Executive Signoff of Staff Reports |
May 24, 2022 | Semi-Monthly Meeting Date Scheduled |
May 24, 2022 | Semi-Monthly Meeting Postponed |
Jun 08, 2022 | Mail Agenda Notice |
Jun 30, 2022 | Semi-Monthly Meeting Date Scheduled |