Action Date | Action Description |
---|---|
Dec 24, 2020 | CHA Worksheet received |
Dec 24, 2020 | Assent Application Received |
Dec 28, 2020 | Administrative Review for Completeness |
Jan 05, 2021 | Bio Team Review for Completeness |
Jan 05, 2021 | Application Accepted |
Jan 06, 2021 | Project Manager |
Jan 21, 2021 | HPHC Review Pending |
Jan 21, 2021 | HPHC Historical Preservation No Effect |
Mar 18, 2021 | Additional Information Received |
Mar 19, 2021 | Additional Information Received |
Mar 23, 2021 | Stipulation Package from Biologist |
Mar 23, 2021 | Biologist Report |
Mar 24, 2021 | Typist for Processing |
Mar 24, 2021 | Executive Sign Off |
Mar 24, 2021 | Sent to Photo Copy |
Mar 24, 2021 | Permit Approved |
Mar 31, 2021 | Land Evidence Date |