Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Dec 28, 2020 | Assent Application Received |
Dec 29, 2020 | Administrative Review for Completeness |
Feb 03, 2021 | Bio Team Review for Completeness |
Feb 03, 2021 | Additional Information Requested from Applicant |
Feb 03, 2021 | Application Accepted |
Feb 03, 2021 | Project Manager |
Feb 03, 2021 | Category A* (Docks) |
Feb 05, 2021 | HPHC Historical Preservation No Effect |
Feb 05, 2021 | HPHC Review Pending |
Feb 17, 2021 | Additional Information Received |
Mar 15, 2021 | Note to File |
Apr 16, 2021 | US Army Corps of Engineers Approval Received |
Apr 21, 2021 | Dock Meeting Scheduled (Admin) |
Apr 22, 2021 | Dock Meeting -- Approval |
Apr 22, 2021 | Biologist Report |
Apr 26, 2021 | Stipulation Package from Biologist |
Apr 26, 2021 | Typist for Processing |
Apr 26, 2021 | Executive Sign Off |
Apr 26, 2021 | Sent to Photo Copy |
Apr 26, 2021 | Permit Approved |
Jun 15, 2021 | Land Evidence Date |