Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Dec 28, 2020 | Assent Application Received |
Dec 29, 2020 | Administrative Review for Completeness |
Jan 05, 2021 | Bio Team Review for Completeness |
Jan 05, 2021 | Application Accepted |
Jan 06, 2021 | Project Manager |
Jan 21, 2021 | HPHC Historical Preservation No Effect |
Jan 21, 2021 | HPHC Review Pending |
Feb 03, 2021 | Additional Information Received |
Feb 08, 2021 | Plans Received |
Feb 09, 2021 | Biologist Report |
Feb 09, 2021 | Stipulation Package from Biologist |
Feb 09, 2021 | Typist for Processing |
Feb 09, 2021 | Executive Sign Off |
Feb 09, 2021 | Sent to Photo Copy |
Feb 09, 2021 | Permit Approved |
Mar 09, 2021 | Land Evidence Date |