Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Dec 30, 2020 | Assent Application Received |
Dec 30, 2020 | Administrative Review for Completeness |
Jan 05, 2021 | Bio Team Review for Completeness |
Jan 05, 2021 | Application Accepted |
Jan 06, 2021 | Project Manager |
Jan 06, 2021 | Category A* (Docks) |
Jan 06, 2021 | Project Manager |
Jan 21, 2021 | HPHC Historical Preservation No Effect |
Jan 21, 2021 | HPHC Review Pending |
Apr 09, 2021 | Additional Information Received |
May 07, 2021 | 30 day Public Notice Issued |
May 12, 2021 | US Army Corps of Engineers Approval Received |
Jun 07, 2021 | Public Notice End Date |
Jun 17, 2021 | Dock Meeting -- Approval |
Jul 28, 2021 | Plans Received |
Aug 04, 2021 | Stipulation Package from Biologist |
Aug 04, 2021 | Biologist Report |
Aug 06, 2021 | Typist for Processing |
Aug 06, 2021 | Executive Sign Off |
Aug 06, 2021 | Sent to Photo Copy |
Aug 06, 2021 | Permit Approved |
Aug 10, 2021 | Permit Mailed |
Aug 18, 2021 | Land Evidence Date |