Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jan 06, 2021 | Assent Application Received |
Jan 07, 2021 | Administrative Review for Completeness |
Jan 07, 2021 | Bio Team Review for Completeness |
Jan 07, 2021 | Project Manager |
Jan 07, 2021 | Application Accepted |
Jan 11, 2021 | Category A* (Docks) |
Jan 21, 2021 | HPHC Historical Preservation No Effect |
Jan 21, 2021 | HPHC Review Pending |
Mar 05, 2021 | 30 day Public Notice Issued |
Apr 05, 2021 | Public Notice End Date |
Apr 09, 2021 | US Army Corps of Engineers Approval Received |
Apr 22, 2021 | Dock Meeting -- Approval |
May 06, 2021 | Stipulation Package from Biologist |
May 06, 2021 | Biologist Report |
May 11, 2021 | Typist for Processing |
May 11, 2021 | Executive Sign Off |
May 11, 2021 | Sent to Photo Copy |
May 11, 2021 | Permit Approved |
Aug 19, 2021 | Land Evidence Date |