Action Date | Action Description |
---|---|
HPHC Review Pending | |
Typist for Processing | |
Dock Post-Construction Certification by Engineer received. | |
Jan 11, 2021 | Assent Application Received |
Jan 12, 2021 | Administrative Review for Completeness |
Jan 26, 2021 | Bio Team Review for Completeness |
Jan 26, 2021 | Additional Information Received |
Jan 26, 2021 | Application Accepted |
Jan 26, 2021 | Project Manager |
Jan 26, 2021 | Biologist Report |
Jan 26, 2021 | Stipulation Package from Biologist |
Jan 27, 2021 | Permit Approved |
Jan 27, 2021 | Executive Sign Off |
Jan 27, 2021 | Sent to Photo Copy |
Feb 08, 2021 | Land Evidence Date |