Dock Post-Construction Certification by Engineer received. | |
Jan 19, 2021 | Assent Application Received |
Jan 21, 2021 | Administrative Review for Completeness |
Feb 01, 2021 | Eng Team Review for Completeness |
Feb 01, 2021 | Application Accepted |
Feb 01, 2021 | Project Manager |
Feb 01, 2021 | Category A* (Docks) |
Feb 01, 2021 | Category A* (Docks) |
Feb 09, 2021 | 30 day Public Notice Issued |
Feb 17, 2021 | HPHC Historical Preservation No Effect |
Mar 09, 2021 | Public Notice End Date |
Mar 26, 2021 | Comments Received |
Apr 26, 2021 | Stipulation Package by Engineer |
Apr 26, 2021 | Typist for Processing |
Apr 26, 2021 | Executive Sign Off |
Apr 26, 2021 | Sent to Photo Copy |
Apr 26, 2021 | Permit Approved |
Apr 26, 2021 | Engineering Report |
May 11, 2021 | Land Evidence Date |
Nov 28, 2023 | Extension of Permit Request |
Nov 28, 2023 | Enforcement Compliance Inspection Required |
Dec 01, 2023 | Process Extension |
Dec 01, 2023 | Typist for Processing |
Dec 01, 2023 | Executive Sign Off |
Dec 01, 2023 | Sent to Photo Copy |
Dec 01, 2023 | Extension Approved |