Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jan 25, 2021 | Assent Application Received |
Jan 26, 2021 | Administrative Review for Completeness |
Feb 01, 2021 | Category A* (Docks) |
Feb 01, 2021 | Bio Team Review for Completeness |
Feb 01, 2021 | Application Accepted |
Feb 01, 2021 | Project Manager |
Feb 05, 2021 | HPHC Review Pending |
Feb 05, 2021 | HPHC Historical Preservation No Effect |
Feb 09, 2021 | 30 day Public Notice Issued |
Feb 09, 2021 | Category A* (Docks) |
Mar 09, 2021 | Public Notice End Date |
Mar 15, 2021 | Additional Information Requested from Applicant |
Mar 16, 2021 | Dock Meeting -- Approval |
Mar 16, 2021 | Additional Information Requested from Applicant |
Apr 07, 2021 | US Army Corp of Engineers Permit Date |
Apr 08, 2021 | Plans Received |
Apr 21, 2021 | Stipulation Package from Biologist |
Apr 21, 2021 | Biologist Report |
Apr 22, 2021 | Typist for Processing |
Apr 22, 2021 | Executive Sign Off |
Apr 22, 2021 | Sent to Photo Copy |
Apr 22, 2021 | Permit Approved |
Apr 29, 2021 | Land Evidence Date |