Action Date | Action Description |
---|---|
Feb 01, 2021 | Assent Application Received |
Feb 03, 2021 | Administrative Review for Completeness |
Feb 15, 2021 | Bio Team Review for Completeness |
Feb 15, 2021 | Application Accepted |
Feb 16, 2021 | Project Manager |
Apr 21, 2021 | HPHC Historical Preservation Comments/Concerns |
Apr 21, 2021 | HPHC Review Pending |
Apr 30, 2021 | HPHC Historical Preservation No Effect |
May 04, 2021 | Biologist Report |
May 06, 2021 | Stipulation Package from Biologist |
May 06, 2021 | Typist for Processing |
May 06, 2021 | Executive Sign Off |
May 06, 2021 | Sent to Photo Copy |
May 06, 2021 | Permit Approved |
Jan 10, 2022 | Land Evidence Date |