Action Date | Action Description |
---|---|
Feb 10, 2021 | Maintenance Certification Request |
Feb 12, 2021 | Administrative Review for Completeness |
Feb 23, 2021 | Eng Team Review for Completeness |
Feb 23, 2021 | Application Accepted |
Feb 23, 2021 | Project Manager |
Mar 01, 2021 | Correspondence Received |
Mar 04, 2021 | Stipulation Package by Engineer |
Mar 04, 2021 | Typist for Processing |
Mar 04, 2021 | Executive Sign Off |
Mar 04, 2021 | Sent to Photo Copy |
Mar 04, 2021 | Permit Approved |
Mar 04, 2021 | Engineering Report |
Mar 16, 2021 | HPHC Review Pending |
Mar 16, 2021 | HPHC Historical Preservation No Effect |
Jul 12, 2021 | Land Evidence Date |