Action Date | Action Description |
---|---|
Feb 04, 2021 | Maintenance Certification Request |
Feb 05, 2021 | Administrative Review for Completeness |
Feb 10, 2021 | Eng Team Review for Completeness |
Feb 10, 2021 | Deficient Application - Owner Notification Sent |
Mar 04, 2021 | Maintenance Certification Request |
Mar 04, 2021 | Application Accepted |
Mar 11, 2021 | Project Manager |
Mar 16, 2021 | HPHC Review Pending |
Mar 16, 2021 | HPHC Historical Preservation No Effect |
Mar 24, 2021 | Permit Approved |
Mar 24, 2021 | Engineering Report |