Action Date | Action Description |
---|---|
Feb 10, 2021 | Assent Application Received |
Feb 12, 2021 | Administrative Review for Completeness |
Feb 16, 2021 | Bio Team Review for Completeness |
Feb 16, 2021 | Deficient Application - Owner Notification Sent |
Mar 18, 2021 | Deficiency Response Received |
Mar 23, 2021 | Additional Information Requested from Applicant |
Apr 06, 2021 | Correspondence Mailed/Faxed/E-mailed |
Apr 09, 2021 | Correspondence Mailed/Faxed/E-mailed |
Apr 21, 2021 | Correspondence Mailed/Faxed/E-mailed |
Apr 30, 2021 | Additional Information Received |
May 05, 2021 | Note to File |
May 05, 2021 | Correspondence Mailed/Faxed/E-mailed |
May 05, 2021 | Additional Information Requested from Applicant |
May 05, 2021 | Note to File |
May 05, 2021 | CHA Worksheet received |
May 11, 2021 | Note to File |
May 12, 2021 | Note to File |
Jun 02, 2021 | Correspondence Mailed/Faxed/E-mailed |
Jun 02, 2021 | Correspondence Received |
Jun 02, 2021 | Note to File |
Jun 10, 2021 | Note to File |
Aug 13, 2021 | Note to File |
Aug 24, 2021 | Note to File |
Aug 25, 2021 | Application Accepted |
Aug 25, 2021 | Project Manager |
Aug 25, 2021 | Bio Team Review for Completeness |
Sep 14, 2021 | Additional Information Requested from Applicant |
Sep 20, 2021 | HPHC Historical Preservation No Effect |
Sep 20, 2021 | HPHC Review Pending |
Oct 15, 2021 | Plans Received |
Oct 19, 2021 | Biologist Report |
Oct 21, 2021 | Site Inspection |
Oct 21, 2021 | Site Inspection |
Oct 28, 2021 | Mail Agenda Notice |
Nov 05, 2021 | Additional Information Received |
Nov 09, 2021 | Semi-Monthly Meeting Date Scheduled |
Nov 09, 2021 | Continuance Requested |
Nov 09, 2021 | Additional Information Received |
Nov 10, 2021 | Mail Agenda Notice |
Nov 23, 2021 | Semi-Monthly Meeting Date Scheduled |
Nov 23, 2021 | Council Approval Granted |
Dec 07, 2021 | Legal Response/Decision |
Dec 07, 2021 | 30 Day Appeal Notification to Owner |
Dec 17, 2021 | Plans Received |
Dec 28, 2021 | Plans Received |
Jan 06, 2022 | Typist for Processing |
Jan 06, 2022 | Permit Approved |
Jan 06, 2022 | Stipulation Package from Biologist |
Jan 13, 2022 | Land Evidence Date |