Action Date | Action Description |
---|---|
Feb 10, 2021 | Freshwater Wetland - Preliminary Determination |
Feb 12, 2021 | Administrative Review for Completeness |
Feb 15, 2021 | Bio Team Review for Completeness |
Feb 15, 2021 | Application Accepted |
Feb 15, 2021 | Project Manager |
Feb 17, 2021 | HPHC Historical Preservation No Effect |
Feb 17, 2021 | HPHC Review Pending |
Mar 22, 2021 | Biologist Report |
Mar 23, 2021 | Stipulation Package from Biologist |
Mar 23, 2021 | Typist for Processing |
Mar 23, 2021 | Executive Sign Off |
Mar 23, 2021 | Sent to Photo Copy |
Mar 23, 2021 | Permit Approved |
Apr 01, 2021 | Land Evidence Date |