Action Date | Action Description |
---|---|
Feb 17, 2021 | CHA Worksheet received |
Feb 17, 2021 | Assent Application Received |
Feb 17, 2021 | Administrative Review for Completeness |
Feb 23, 2021 | Bio Team Review for Completeness |
Feb 23, 2021 | Application Accepted |
Feb 23, 2021 | Project Manager |
Mar 03, 2021 | HPHC Review Pending |
Mar 03, 2021 | HPHC Historical Preservation No Effect |
Apr 06, 2021 | Plans Received |
Apr 08, 2021 | Stipulation Package from Biologist |
Apr 08, 2021 | Biologist Report |
Apr 12, 2021 | Typist for Processing |
Apr 12, 2021 | Executive Sign Off |
Apr 12, 2021 | Sent to Photo Copy |
Apr 12, 2021 | Permit Approved |
May 07, 2021 | Land Evidence Date |
Jul 07, 2021 | Modification Request |
Jul 09, 2021 | Administrative Review for Completeness |
Jul 09, 2021 | CHA Worksheet received |
Jul 27, 2021 | Bio Team Review for Completeness |
Jul 28, 2021 | HPHC Historical Preservation No Effect |
Sep 02, 2021 | Biologist Report |
Sep 02, 2021 | Stipulation Package from Biologist |
Sep 07, 2021 | Typist for Processing |
Sep 07, 2021 | Executive Sign Off |
Sep 07, 2021 | Sent to Photo Copy |
Sep 07, 2021 | Modification Approved |
Sep 27, 2021 | Land Evidence Date |