Action Date | Action Description |
---|---|
Feb 18, 2021 | Preliminary Determination Request (Coastal) |
Feb 18, 2021 | Administrative Review for Completeness |
Mar 05, 2021 | Bio Team Review for Completeness |
Mar 05, 2021 | Category W assigned |
Mar 05, 2021 | Application Accepted |
Mar 05, 2021 | Project Manager |
Mar 18, 2021 | HPHC Historical Preservation No Effect |
Mar 23, 2021 | Additional Information Requested from Applicant |
Apr 06, 2021 | Additional Information Requested from Applicant |
Apr 15, 2021 | Note to File |
Apr 15, 2021 | Plans Received |
May 20, 2021 | Correspondence Received |
May 20, 2021 | Correspondence Mailed/Faxed/E-mailed |
Jun 10, 2021 | Correspondence Mailed/Faxed/E-mailed |
Jun 23, 2021 | Additional Information Received |
Jul 01, 2021 | Additional Information Received |
Jul 15, 2021 | Additional Information Requested from Applicant |
Jul 20, 2021 | Plans Received |
Aug 13, 2021 | Stipulation Package from Biologist |
Aug 13, 2021 | Biologist Report |
Aug 20, 2021 | Typist for Processing |
Aug 20, 2021 | Executive Sign Off |
Aug 20, 2021 | Sent to Photo Copy |
Aug 20, 2021 | Permit Approved |
Aug 24, 2021 | Permit Mailed |
Sep 02, 2021 | Land Evidence Date |