Action Date | Action Description |
---|---|
Biologist Report | |
Mar 05, 2021 | Freshwater Wetland - Preliminary Determination |
Mar 09, 2021 | Administrative Review for Completeness |
Mar 23, 2021 | Bio Team Review for Completeness |
Mar 23, 2021 | Application Accepted |
Mar 23, 2021 | Project Manager |
May 19, 2021 | HPHC Historical Preservation No Effect |
May 19, 2021 | HPHC Review Pending |
Jul 01, 2021 | Executive Sign Off |
Jul 01, 2021 | Sent to Photo Copy |
Jul 01, 2021 | Stipulation Package from Biologist |
Jul 01, 2021 | Typist for Processing |
Jul 01, 2021 | Permit Approved |
Jul 01, 2021 | Biologist Report |
Aug 26, 2021 | Land Evidence Date |
Mar 18, 2024 | Modification Request |
Mar 25, 2024 | Administrative Review for Completeness |
Mar 27, 2024 | Bio Team Review for Completeness |
Mar 27, 2024 | Project Manager |
Apr 05, 2024 | HPHC Historical Preservation No Effect |