Action Date | Action Description |
---|---|
Assent Requirement | |
Mar 10, 2021 | Assent Application Received |
Mar 10, 2021 | Administrative Review for Completeness |
Mar 10, 2021 | CHA Worksheet received |
Mar 15, 2021 | Bio Team Review for Completeness |
Mar 15, 2021 | Application Accepted |
Mar 15, 2021 | Project Manager |
May 19, 2021 | HPHC Historical Preservation No Effect |
May 19, 2021 | HPHC Review Pending |
May 24, 2021 | Stipulation Package from Biologist |
May 24, 2021 | Biologist Report |
May 25, 2021 | Typist for Processing |
May 25, 2021 | Executive Sign Off |
May 25, 2021 | Sent to Photo Copy |
May 25, 2021 | Permit Approved |
Jun 04, 2021 | Land Evidence Date |
Mar 07, 2024 | Extension of Permit Request |
May 17, 2024 | Enforcement Compliance Inspection Required |
May 17, 2024 | Process Extension |
May 17, 2024 | Extension Approved |