Action Date | Action Description |
---|---|
Mar 26, 2021 | Assent Application Received |
Mar 31, 2021 | Administrative Review for Completeness |
Mar 31, 2021 | CHA Worksheet received |
Apr 08, 2021 | Bio Team Review for Completeness |
Apr 08, 2021 | Application Accepted |
Apr 12, 2021 | Project Manager |
Apr 15, 2021 | Additional Information Requested from Applicant |
Apr 21, 2021 | HPHC Historical Preservation No Effect |
Apr 21, 2021 | HPHC Review Pending |
Apr 23, 2021 | Note to File |
Apr 29, 2021 | Phone Call |
Apr 29, 2021 | Correspondence Mailed/Faxed/E-mailed |
May 04, 2021 | Additional Information Received |
May 04, 2021 | Stipulation Package from Biologist |
May 04, 2021 | Biologist Report |
May 06, 2021 | Typist for Processing |
May 06, 2021 | Executive Sign Off |
May 06, 2021 | Sent to Photo Copy |
May 06, 2021 | Permit Approved |
May 12, 2021 | Land Evidence Date |