Mar 26, 2021 Assent Application Received
Mar 29, 2021 Administrative Review for Completeness
Apr 01, 2021 Eng Team Review for Completeness
Apr 01, 2021 Application Accepted
Apr 01, 2021 Project Manager
May 14, 2021 Additional Information Received
May 19, 2021 HPHC Historical Preservation No Effect
May 19, 2021 HPHC Review Pending
May 20, 2021 Stipulation Package by Engineer
May 20, 2021 Typist for Processing
May 20, 2021 Engineering Report
May 25, 2021 Permit Approved
May 26, 2021 Assent Correction Request Received
May 26, 2021 Assent Correction Mailed
Jun 07, 2021 Land Evidence Date

Details:

File No
2021-03-116
Town
Westerly
First Name
Town of Westerly
Last Name
Street
Breen Road & Pasadena Avenue
Location
Breen Road & Pasadena Avenue
Plat/Map
Lot/Block
Decision Date
May 25, 2021
Dock Reg.No
Project
Rehabilitate existing pavement & improve stormwater with in right of way
Description
Recreation Structure (Public)