Action Date | Action Description |
---|---|
Mar 30, 2021 | Assent Application Received |
Mar 31, 2021 | Administrative Review for Completeness |
Mar 31, 2021 | CHA Worksheet received |
Apr 01, 2021 | Additional Information Requested from Applicant |
Apr 05, 2021 | Additional Information Received |
Apr 05, 2021 | Application Accepted |
Apr 05, 2021 | Project Manager |
Apr 05, 2021 | Bio Team Review for Completeness |
May 18, 2021 | Note to File |
May 19, 2021 | HPHC Historical Preservation No Effect |
May 19, 2021 | HPHC Review Pending |
May 21, 2021 | Biologist Report |
May 21, 2021 | Stipulation Package from Biologist |
May 24, 2021 | Typist for Processing |
May 24, 2021 | Executive Sign Off |
May 24, 2021 | Sent to Photo Copy |
May 24, 2021 | Permit Approved |
Jun 15, 2021 | Land Evidence Date |
Jul 07, 2021 | Modification Request |
Jul 09, 2021 | Administrative Review for Completeness |
Jul 09, 2021 | CHA Worksheet received |
Jul 13, 2021 | Bio Team Review for Completeness |
Aug 05, 2021 | HPHC Historical Preservation No Effect |
Aug 05, 2021 | HPHC Review Pending |
Aug 27, 2021 | Additional Information Requested from Applicant |
Aug 30, 2021 | Correspondence Mailed/Faxed/E-mailed |
Aug 31, 2021 | Plans Received |
Sep 07, 2021 | Additional Information Requested from Applicant |
Sep 07, 2021 | Additional Information Received |
Sep 07, 2021 | Biologist Report |
Sep 10, 2021 | Typist for Processing |
Sep 13, 2021 | Executive Sign Off |
Sep 13, 2021 | Sent to Photo Copy |
Sep 13, 2021 | Modification Approved |
Nov 05, 2021 | Duplicate Original Assent requested/mailed |
Nov 12, 2021 | Land Evidence Date |